Baker square Community Events

We are pleased to inform you that the installation of the EV charging stations will begin on Monday, October 27th. This marks the first phase of the project, which is expected to take approximately one week to complete.

Following this phase, an electrical shutdown of the Water Mill building will be scheduled with Eversource to connect the new charging stations to the existing Water Mill electrical transformer. Please see the project diagram below for your reference.

Below is the current construction schedule:

  • Monday, October 27th & Tuesday, October 28th: Inovis Energy will be working in the first seven visitor parking spaces. These spaces will be unavailable for use throughout the entire week. All visitor’s vehicles must be removed by 7am on Monday, October 27th!
  • Wednesday, October 29th & Thursday, October 30th: Trenching work will take place between the visitor parking spaces and the Water Mill building. Contractors will complete the work in sections to maintain traffic flow through the area. We kindly ask all drivers to proceed with extreme caution and drive slowly while work is underway.
  • Friday, October 31st: Contractors will complete site cleanup and any remaining punch list items.

We appreciate your patience and cooperation! We are available should you have any questions or concerns. Status updates will be added to this post!